ericscher
Well-Known Member
I'm struggling to put together an estimate for a customer who wants a new parking area. Normally when I do this I am just laying in material on top of a pre-existing construction drive. This time I need to excavate the area myself.
The excavation is fairly simple in that I'm only going down about 10 inches and I expect to produce about 100 yards of spoils before it fluffs.
Soil is former farmland converted to residential and likely to be pretty moist. I have no test holes to see if I'll be dealing more with soil or clay, nor will I be getting them.
I'm using 30" ditch bucket with a roughly 5 cubic foot capacity and a 3500 size dump truck that will handle 3 ton loads.
Spoils are being disposed of on site and no single trip is likely to be more 100 yards, so my ratio of digging time to waiting time should be pretty good. At LEAST 40:20, and that's being conservative.
My work doesn't involve a whole lot of excavation and almost all of it is just culvert work so I don't have the amount of experience needed to answer one simple question...
Under the described circumstances, how much TIME will it take?
Even if I price this open ended at $XXX/hr, the customer will still want to know a range.
Going on just the math and assuming 6 bucket loads per yard that would be 600 buckets. Assuming it takes 5 minutes to load 6 buckets that's 1 yard in 5 minutes and 8 yards in 40 minutes, or 8 yards per hour if I the 40:20 work to idle time is correct.
That's 12.5 hours to excavate 100 yards, assuming all my assumptions are correct and nothing goes wrong.
At $150/Hr that comes out to $1,875.
If I bid the excavation work at $1,000/day for two days that should cover it.
SHOULD.
But are my assumptions worth a damn? Am I just pulling this out of my 4th point of contact? (old paratrooper term)
What do you guys think?
The excavation is fairly simple in that I'm only going down about 10 inches and I expect to produce about 100 yards of spoils before it fluffs.
Soil is former farmland converted to residential and likely to be pretty moist. I have no test holes to see if I'll be dealing more with soil or clay, nor will I be getting them.
I'm using 30" ditch bucket with a roughly 5 cubic foot capacity and a 3500 size dump truck that will handle 3 ton loads.
Spoils are being disposed of on site and no single trip is likely to be more 100 yards, so my ratio of digging time to waiting time should be pretty good. At LEAST 40:20, and that's being conservative.
My work doesn't involve a whole lot of excavation and almost all of it is just culvert work so I don't have the amount of experience needed to answer one simple question...
Under the described circumstances, how much TIME will it take?
Even if I price this open ended at $XXX/hr, the customer will still want to know a range.
Going on just the math and assuming 6 bucket loads per yard that would be 600 buckets. Assuming it takes 5 minutes to load 6 buckets that's 1 yard in 5 minutes and 8 yards in 40 minutes, or 8 yards per hour if I the 40:20 work to idle time is correct.
That's 12.5 hours to excavate 100 yards, assuming all my assumptions are correct and nothing goes wrong.
At $150/Hr that comes out to $1,875.
If I bid the excavation work at $1,000/day for two days that should cover it.
SHOULD.
But are my assumptions worth a damn? Am I just pulling this out of my 4th point of contact? (old paratrooper term)
What do you guys think?