Hey guys:
Got a demolition job for my cat 430E backhoe. Pics attached.
The building to the left with the exposed masonry blocks is what needs to be removed. It is 27 feet long x 12 feet wide x 9 feet tall. It has concrete stiffeners and a reinforced concrete roof slab.
I'm thinking a water hose to keep down the dust during demolition, a hammer extension to separate the roof slab of building to be demolished from the main building to be untouched.
So my question is, am I missing anything? Could this be done without a demolition hammer extension? How long should the demolition take with and without the hammer?
Thanks in advance.
Andre
Got a demolition job for my cat 430E backhoe. Pics attached.
The building to the left with the exposed masonry blocks is what needs to be removed. It is 27 feet long x 12 feet wide x 9 feet tall. It has concrete stiffeners and a reinforced concrete roof slab.
I'm thinking a water hose to keep down the dust during demolition, a hammer extension to separate the roof slab of building to be demolished from the main building to be untouched.
So my question is, am I missing anything? Could this be done without a demolition hammer extension? How long should the demolition take with and without the hammer?
Thanks in advance.
Andre