skyking1
Senior Member
I would keep going with really good material on top of the keyway. That is what I meant. If you had some really impervious clay but not much of it, keep going up with it.
On the Cowlitz falls dam, we were racing the river coming up and dozer diving off the haul road, and then cut a slot in it and poured a concrete core.Every dam that I have been involved with building the keyway is the most stressful part. Usually have a temp dam holding the water back while you hustle to get the muck out and dry dirt back in and compacted before the water goes over the temp dam. Your situation might be different.
This is very helpful, thank you!a serious project as the consequences of the dam failure could be catastrophic. Also, I can't imagine a scenario where even the earthmoving and compaction portion alone could cost less than $3.00 per CY in place. Then add control structure and spillway costs and this would easily be a $50,000 or more project in my neck of the
Will double wall corrugated pipe be water tight enough at the connections, for an underwater connection? I guess I assumed it would not be, therefore didn’t consider vertical culvert pipe as an option. You can buy 90 degree fittings for it though - this may be a consideration..As to the overflow, if you use a horizontal culvert instead of a vertical stand pipe there are a couple downfalls you need to be aware of. First, if you use a 12” culvert for example, the level of the pond has to rise 12” before full flow is achieved. With a standpipe full flow is achieved with only a 2-3” rise of the pond level. Be sure you have plenty of freeboard height on the dam and a good spill of emergency spillway (which you should have both regardless.) Second, erosion is a real problem with a culvert for an overflow. During heavy flow it creates a vortex near the bank washing the dirt away around it. Use plenty of rip rap around the pipe and make sure the downstream side goes all the way to the bottom of the dam.
There is a third option, which is to build a standpipe but closer to the finished height. In this setup you’d put a horizontal pipe in with an L and maybe 4-5’ of vertical pipe. The stand pipe may only be 5-10’ away from the shore in this scenario, but would still provide most of the benefits with much less cost. You could even use 12” double wall black culvert pipe if you could find an L.
Will double wall corrugated pipe be water tight enough at the connections, for an underwater connection? I guess I assumed it would not be, therefore didn’t consider vertical culvert pipe as an option. You can buy 90 degree fittings for it though - this may be a consideration..
.
The ones I’ve seen are not water tight enough to be submerged, but in that design they don’t need to be as the L is burried in about 3-4’ of dirt, often with some concrete poured around the connection itself. You can use the same design (shallow, close to shore standpipe) with PVC, we often use that setup when repairing ponds with a leak or some other problem. Usually fill the existing pipe with concrete and install a new standpipe closer to shore, then you don’t have to drain the pond completely or trench 20’ deep
Yeesh. I have a ~100 gallon tank on my 977.Cat was generally good at sizing fuel capacity for a full days work.
Run it hard a day for 10-12 hours, see where the fuel level sits.Yeesh. I have a ~100 gallon tank on my 977.